Party autonomy does not usurp the power of our courts
At a glance
- In AIG South Africa Limited v Molefe [2025] JDR 3456 (GP), the court was required to determine whether sufficient good cause had been shown for it to set aside an arbitration agreement and order that the dispute between the parties not be referred to arbitration.
- The court, in exercising its discretion, held that it would be untenable for AIG South Africa Limited’s claims to be dealt with in a piecemeal fashion under multiple proceedings with the “attendant unnecessary and unjustifiable wasteful increase in costs and witnesses potentially testifying on more than one occasion on the same facts”.
- This case illustrates that our courts will not shy away from exercising their discretion, on good cause shown, to bypass arbitration clauses in agreements.
Background
AIG issued a management liability insurance policy (Policy) to Eskom as the policy holder in 2017, in terms of which AIG agreed that in consideration for the payment of the premium due under the Policy, it would provide liability cover to Eskom’s directors, officers and employees on the terms set out in the Policy.
Mr Brian Molefe (Molefe), the former Group CEO of Eskom was covered under the Policy as an insured person, and was eligible to be indemnified by AIG, subject to the terms and conditions of the Policy.
It later came to pass that Molefe became embroiled in various legal proceedings and sought an indemnity from AIG under the Policy in respect of his legal costs in opposing these proceedings.
AIG agreed to pay Molefe’s defence costs on condition that if it was found by a court that Molefe had gained a profit or an advantage to which he was not legally entitled or that there was a commission of a dishonesty or deliberate fraudulent act, that Molefe would have to repay those costs that had been disbursed.
In correspondence exchanged between the parties dated 27 October 2017 (2017 Agreement), AIG advised Molefe that it would advance his defence costs on a “without prejudice” basis and on condition that should it transpire in due course that Molefe was not entitled to indemnification under the Policy, Molefe would refund such costs in full to AIG.
AIG disbursed approximately R4,398,849 to Molefe for his defence costs in terms of the Policy, whereafter judgments from both the Supreme Court of Appeal and Constitutional Court in the legal proceedings instituted against Molefe found that he had acted unlawfully.
Flowing from these judgments, AIG instituted proceedings against Molefe for repayment of the defence costs disbursed to him in terms of the Policy.
Submissions by the parties
AIG contended that it was entitled, pursuant to the exclusion in the Policy, the 2017 Agreement and Molefe being unjustifiably enriched at its expense, to repayment of the funds disbursed by it to Molefe.
Molefe took issue with the non-joinder of Eskom in the action proceedings on the basis that it, and not Molefe, was the holder and signatory of the Policy. Consequently, as Molefe’s arguments went, he could not be held liable to repay the costs paid out for his defence on his behalf and AIG must look to Eskom for repayment of the disbursed funds.
In addition, Molefe relied on clause 7.6 of the Policy, which provided that:
“[E]xcept as otherwise specifically provided, any dispute regarding any aspect of this policy or any matter relating to cover thereunder which cannot be resolved by agreement within 30 days, shall be referred to binding arbitration by either party upon 7 days’ notice to the other in terms of the Arbitration Act.”
Moreover, Molefe argued that he did not agree to the provisions of the 2017 Agreement and that AIG’s claims against him, although misplaced, should be determined under the arbitration clause of the Policy.
Section 3(2) of the Arbitration Act provides that:
“The court may at any time on the application of any party to an arbitration agreement, on good cause shown – set aside the arbitration agreement; or order that any particular dispute referred to in the arbitration agreement shall not be referred to arbitration; or order that the arbitration agreement shall cease to have effect with reference to any dispute referred.”
The court’s decision
In addressing the parties’ respective submissions, the court found that AIG’s claim based on the 2017 Agreement was self-standing and independent of the Policy. Therefore, it was not a dispute contemplated in the arbitration clause of the Policy.
It also found that AIG’s claim for unjustified enrichment was not a claim regarding an aspect of the Policy or matter related to cover under it. This claim too was self-standing, independent of the Policy and not contemplated in the arbitration clause of the Policy.
The court, in exercising its discretion, held that it would be untenable for AIG’s claims to be dealt with in a piecemeal fashion under multiple proceedings with the “attendant unnecessary and unjustifiable wasteful increase in costs and witnesses potentially testifying on more than one occasion on the same facts”.
Relying on the decision in Multi-Links Telecommunications Ltd v Africa Prepaid Services Nigeria Ltd [2014] (3) SA 265 (GP) that a multiplicity of claims proceedings in different forums on the same facts should be avoided in light of conflicting decisions, the court held that all three of AIG’s claims should be dealt with simultaneously in a single proceeding before one forum to facilitate the administration of justice.
Takeaway
This case illustrates that our courts will not shy away from exercising their discretion, on good cause shown, to bypass arbitration clauses in agreements.
Such exercise of discretion does not throw party autonomy to the wayside, but aligns with what is practical and facilitates the administration of justice in a given situation, on the facts of the case before it.
The information and material published on this website is provided for general purposes only and does not constitute legal advice. We make every effort to ensure that the content is updated regularly and to offer the most current and accurate information. Please consult one of our lawyers on any specific legal problem or matter. We accept no responsibility for any loss or damage, whether direct or consequential, which may arise from reliance on the information contained in these pages. Please refer to our full terms and conditions. Copyright © 2025 Cliffe Dekker Hofmeyr. All rights reserved. For permission to reproduce an article or publication, please contact us cliffedekkerhofmeyr@cdhlegal.com.